Day 9 - Tuesday, 24th November 2020



 Start of day 9 and this above is how the day began.




Finish of day 9 and the above is how it ended.

Roof all complete.

Still a lot to do of course, including the plumber replacing the two radiators in the office and the bedroom and to install one in the conservatory plus he's going to replace all the thermostatic radiator valves in the bungalow as they are old. Then the electrician for sockets including TV and radio and some lighting.  The plasterer and of course the floor to be finished then finally covered. Oh and they've got to put the two doors in yet, which could be tomorrow.